| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 07 Jan 2023 | TS ISSUED AND WORK TENDERED | Kannur PH Dn EE | |
| 04 Jan 2023 | Estimate under Scrutiny | Perlassery Sn 2 AE | |
| 30 Dec 2022 | Estimate under Scrutiny | Perlassery Sn 2 AE | |
| 26 Dec 2022 | Estimate under Scrutiny | Perlassery Sn 2 AE | |
| 21 Dec 2022 | Estimate under Scrutiny | Perlassery Sn 2 AE | |
| 13 Dec 2022 | Estimate under Scrutiny | Kannur PH Dn EE | |
| 08 Dec 2022 | Estimate submitted to SE for TS | Kannur PH Dn EE | |
| 19 Sep 2022 | Estimate submitted for OD approval | Perlassery Sn 2 AE | |
| 11 Sep 2022 | Estimate submitted for OD approval | Perlassery Sn 2 AE | |
| 09 Sep 2022 | Estimate submitted for OD approval | Perlassery Sn 2 AE |