| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 27 Mar 2024 | Site handed over to the contractor.Work not started. | Perlassery Sn 2 AE | |
| 18 Mar 2024 | Site handed over to the contractor.Work not started. | Perlassery Sn 2 AE | |
| 11 Mar 2024 | Site handed over to the contractor.Work not started. | Perlassery Sn 2 AE | |
| 28 Feb 2024 | Site handed over to the contractor.Work not started. | Perlassery Sn 2 AE | |
| 14 Feb 2024 | Site handed over to the contractor.Work not started. | Perlassery Sn 2 AE | |
| 06 Feb 2024 | Site handed over to the contractor.Work not started. | Perlassery Sn 2 AE | |
| 30 Jan 2024 | Site handed over to the contractor,but work not started. | Perlassery Sn 2 AE | |
| 11 Jan 2024 | AGREEMENT EXECUTED | Perlassery Sn 2 AE | |
| 05 Jan 2024 | AGREEMENT EXECUTED | Perlassery Sn 2 AE | |
| 30 Dec 2023 | AGREEMENT EXECUTED | Perlassery Sn 2 AE |